Pall Mall

Posted on 7th July, 2012

Cobra Steel were asked to assist on 55t of temporary support steel on a job in Pall Mall, London.

 

A team of erectors were sent in to help load out the steelwork and start on the installation.

 

 

The first 5 floors from 7th to 3rd were loaded out over the coarse of a weekend using a crane, with the lower floors being done in later stages loading out with a hiab.

 

All of the erection had to coincide with the demolition of the building.